DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›Tuvalu Coastal Adaptation project update
Beach Nourishment

September 21, 2025 · about 11 months ago

Tuvalu Coastal Adaptation project update

Hall Contracting continues to make great progress on the Tuvalu Coastal Adaptation Project phase 1A. According to the latest update, overall construction is now 93% complete, with civil works at 98% and reclamation at 88%. Work at the southern boat harbor is nearing completion, while the northern wa

1 minutes read
  • LinkedIn
  • X
  • Email
Tuvalu Coastal Adaptation project update
Photo courtesy of the UNDP Pacific Office in Fiji

Share this article

Hall Contracting continues to make great progress on the Tuvalu Coastal Adaptation Project phase 1A.

According to the latest update, overall construction is now 93% complete, with civil works at 98% and reclamation at 88%.

Work at the southern boat harbor is nearing completion, while the northern wall construction continues with design adjustments to suit property boundaries.

Also, planning for the northern extension (TCAP 1B) is progressing, with firms selected to begin environmental and social impact assessment and environmental and social management plan preparation and engineering designs.

This coastal adaptation project is part of a broader commitment to building a resilient future for Tuvalu by reclaiming approximately eight hectares of new, safe, raised land.

The Tuvalu Coastal Adaptation Project 1A is scheduled to be completed in the next few weeks, with a full handover to the Government by mid-2026.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach NourishmentCoastal ProtectionDredgingLand Reclamation

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  2. 2Stockton closes boat launch due to dredging work
  3. 3E-touch Dredgers: Work on new TSHD progresses steadily
  4. 4USACE begins Lower Charleston Harbor maintenance dredging

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free