The Port of San Diego said that the repair work on the west side of the Shelter Island Boat Launch Ramp is underway.
Work on the west side of the launch facility will include:
In June 2023, the west floating dock sustained significant damage due to sand accumulation underneath it, which caused the dock to bottom out at low tide.
The Port’s engineering department and consultants immediately launched a comprehensive investigation to determine the cause and extent of the damage and to begin developing a repair and restoration plan.
According to the Port, this repair work is anticipated to be completed in April.