DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Duck beach nourishment project rescheduled for March
Operations & Maintenance

December 13, 2022 · about 3 years ago

Duck beach nourishment project rescheduled for March

The Town of Duck, North Carolina, has revealed new information about the upcoming beach nourishment project. According to the latest release from the town, Duck beach nourishment will start later than previously planned, most likely in mid-March. Yesterday, the town announced that due to equipment i

1 minutes read
  • LinkedIn
  • X
  • Email
Duck beach nourishment project rescheduled for March
USACE

The Town of Duck, North Carolina, has revealed new information about the upcoming beach nourishment project.

According to the latest release from the town, Duck beach nourishment will start later than previously planned, most likely in mid-March.

Yesterday, the town announced that due to equipment issues, minor weather- related delays, and commitment to another time- sensitive job, the contractor Weeks Marine has fallen behind the original schedule.

“Dare County, with whom this contract is made, and our coastal engineers, Weeks Marine staff members, and our team are working on a contract modification to ensure that our project is properly constructed in the spring,” the town said. “This will include assurances that any beach/ dune losses between now and when the project is completed are properly replaced and that Weeks Marine will be responsible for all costs associated with additional sand and delays.”

They also added that this change in schedule, while unfortunate, will have beach nourishment completed before the busier time of year and after the typically heavier part of the winter storm season. The town remains confident that the job will be completed according to the new schedule by no later than mid- May.

The Duck beach project includes nourishment of approximately 1.6 miles of shoreline from the Army Corps Pier north to Skimmer Way at a construction cost of $7.4 million.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free