DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Dredge Liberty Island wraps up Avon beachfill project
Operations & Maintenance

July 27, 2022 · about 4 years ago

Dredge Liberty Island wraps up Avon beachfill project

Great Lakes Dredge and Dock Co. has completed the 1 million cubic yard beach nourishment project in Avon, North Carolina. As reported, the last load of sand was delivered by the hopper dredge Liberty Island at 11 p.m. on Tuesday, July 26, 2022, between Yucca Street and Pampas Drive. The project incl

2 minutes read
  • LinkedIn
  • X
  • Email
Dredge Liberty Island wraps up Avon beachfill project
Coastal Science & Engineering

Great Lakes Dredge and Dock Co. has completed the 1 million cubic yard beach nourishment project in Avon, North Carolina.

As reported, the last load of sand was delivered by the hopper dredge Liberty Island at 11 p.m. on Tuesday, July 26, 2022, between Yucca Street and Pampas Drive.

The project included nourishing approximately 2.5 miles of oceanfront from Due East Road to the southernmost boundary of Avon and constructing a new frontal dune (6 feet above the dry-sand beach) south of the Avon Pier.

The dredge Ellis Island delivered the first load of sand in Avon at 1:40 p.m. on Sunday, June 19, 2022. Through the strategic use of two dredges, GLDD completed the project in 38 days, including an 8-day pause from June 30, 2022, through July 7, 2022.

After the last load of sand was delivered onto the beach, the Liberty Island headed out to Norfolk, Virginia, for repairs, maintenance and refueling. The dredge is expected to return to Dare County to resume beach nourishment operations in Buxton today, July 28, or Friday, July 29, 2022.

According to GLDD, equipment demobilization began immediately after the last load of nourishment sand was placed on the beach and is ongoing.

The newly nourished beach was graded, smoothed and reopened to the public on the morning of Wednesday, July 27, 2022.

Equipment and shore pipes will be transported through ORV Ramp 38 and demobilized out of Avon over the next two weeks.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & MaintenanceVessels

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free