DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›PMG takes part in the Townsville Channel upgrade project
Operations & Maintenance

May 30, 2022 · about 4 years ago

PMG takes part in the Townsville Channel upgrade project

Pacific Marine Group has been engaged by Hall Contracting to undertake piling works as part of the Temporary Unloading Facility construction package which is part of the Port of Townsville Channel Upgrade Project. According to PMG, the works being completed under stringent permit conditions that inc

1 minutes read
  • LinkedIn
  • X
  • Email
PMG takes part in the Townsville Channel upgrade project
PMG

Pacific Marine Group has been engaged by Hall Contracting to undertake piling works as part of the Temporary Unloading Facility construction package which is part of the Port of Townsville Channel Upgrade Project.

According to PMG, the works being completed under stringent permit conditions that include:

The scope of works includes installing 30 x 750dia Anchor Piles, 6 x 950dia Breasting Piles, and 137 x AZ36-700N Double Sheet Piles (just shy of 200m of sheet pile wall).

“To drive the piles we used equipment including an ICE55NF Vibratory Hammer and IHC S-70 Sheetlegs Impact Hammer paired with our in house ICE vibro hammers and Junttan 7/9A Impact Hammer. This pile driving gear has been operated from our marine plant that includes PMG151, PMG181 & PMG182 Construction Barges paired with our Sany 100T & 150T Crawler Cranes,” said PMG in the announcement.

“Brandon, Andrew and crew completed the works which took significant commitment from their whole team and support of all of PMG’s departments out of the Townsville Marine Precinct,” concluded the company.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free