DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Brighton Marina dredging well underway
Operations & Maintenance

June 20, 2021 · about 5 years ago

Brighton Marina dredging well underway

ML Dredging recently won a contract for the excavation of 55,000m3 of naturally deposited sand and silt from the UK’s largest marina, the Brighton Marina. This dredging scheme will not only deepen the entrance to the marina but also widen the approach channel. Approximately 15,000m3 will be removed

1 minutes read
  • LinkedIn
  • X
  • Email
Brighton Marina dredging well underway
ML Dredging

ML Dredging recently won a contract for the excavation of 55,000m3 of naturally deposited sand and silt from the UK’s largest marina, the Brighton Marina.

This dredging scheme will not only deepen the entrance to the marina but also widen the approach channel.

Approximately 15,000m3 will be removed from the entrance before heading inside the marina to deepen berths around the visitors pontoon and main fairway leading to the fuel dock.

The programme is now well under way with the contractor first finishing work in the entrance channel this week, after which the team will proceed with further dredging in the marina basin, announced the officials.

Witton II backhoe dredger is carrying out the excavation. Witton II carries a Liebherr 964 with a bucket capacity of 4m3. Dredged material is being loaded into the 460m3 self propelled split hopper barge Split Three.

According to the contractor, the spoil site is located nearby just to the East of the Marina. The crew aim is to dredge a minimum of three cargos (approx. 1,100m3) per day.

“Brighton Marina is the largest in the UK boasting over 1,300 berths. We are very proud to be entrusted with the dredging operations at this prestigious marina. Thank you to the very professional staff at Brighton Marina for your assistance,” said ML Dredging in the release.

The contract is scheduled to be completed within 2-3 months weather permitting.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free