DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Bandy Creek dredging underway
Operations & Maintenance

May 11, 2021 · about 5 years ago

Bandy Creek dredging underway

The Western Australia Department of Transport (DoT) is working with the Shire of Esperance to widen Castletown Beach with a special trial that will see dredged sand pumped from Bandy Creek. Dredged sand from the entrance channel at the Bandy Creek Boat Harbour will be pumped 3.6 kilometres through t

1 minutes read
  • LinkedIn
  • X
  • Email
Bandy Creek dredging underway
Cooper Group of Companies (CGC)

The Western Australia Department of Transport (DoT) is working with the Shire of Esperance to widen Castletown Beach with a special trial that will see dredged sand pumped from Bandy Creek.

Dredged sand from the entrance channel at the Bandy Creek Boat Harbour will be pumped 3.6 kilometres through temporary onshore pipelines to the beach to avoid future trucking campaigns to replenish sand levels.

An estimated 40,0000 cubic metres of sand will be pumped to replace eroding sections of the beach, widening the coastline, protecting the foreshore and enhancing the beach for locals and visitors to the area, said DoT in the release.

DoT Maritime Executive Director Steve Jenkins commented that recent hydrographic surveys confirmed maintenance dredging was required in the area to restore the entrance channel depths and ensure safe access to Bandy Creek Boat Harbour for skippers.

“Maintenance dredging at the harbour is undertaken every two years by DoT to ensure all commercial fishing, charter industry and recreational vessels have safe access to the facility,” Mr Jenkins said.

The dredging, pumping and sand replenishment trial started in early-May with works allowed between Monday and Saturday from 7:00am to 6:00pm.

DoT also issued a warning for skippers operating in the dredge area and people accessing the beach to be aware of the special safety arrangements implemented for the dredging and sand replenishment works. Sections of the beach may be temporarily closed to ensure public safety.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free