DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Corpus Christi: Callan crews busy working on DMPA
Infrastructure

December 1, 2020 · about 5 years ago

Corpus Christi: Callan crews busy working on DMPA

Construction on the United States Army Corps of Engineers’ project to deepen and widen the Corpus Christi Ship Channel is underway, Callan Marine informs. Awarded this past April, this project will provide an additional 130 feet of width and 7 feet of depth to the Lower Reaches of the channel. Dredg

1 minutes read
  • LinkedIn
  • X
  • Email
Corpus Christi: Callan crews busy working on DMPA
Callan

Construction on the United States Army Corps of Engineers’ project to deepen and widen the Corpus Christi Ship Channel is underway, Callan Marine informs.

Awarded this past April, this project will provide an additional 130 feet of width and 7 feet of depth to the Lower Reaches of the channel.

Dredging requires removal of 12 million cubic yards of both maintenance and new work and will take an estimated year and a half to complete.

To accommodate the channel deepening, Callan has begun work rehabilitating and raising levees on the DMPA (Dredging Material Placement Area).

Additionally, multiple oil and gas pipelines will be decommissioned and removed along the channel.

The cutter suction dredge General MacArthur is expected to arrive in early 2021.

“We are extremely appreciative of the Army Corps of Engineers for acknowledging the strategic national importance of executing the Corpus Christi Ship Channel Improvement Project,” said Sean Strawbridge , Port of Corpus Christi Chief Executive Officer.

“As the largest export gateway for U.S. produced energy destined for global demand markets, a deeper and wider ship channel will solidify the competitiveness of American energy on the world stage.”

Estimated completion for this phase of the Corpus Christi Ship Channel Improvement Project is early 2022, with improvements to Ingleside by fourth quarter of 2021.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free