DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Leatherman Terminal project on the home stretch
Infrastructure

October 6, 2020 · about 5 years ago

Leatherman Terminal project on the home stretch

Construction of SC Ports’ Hugh K. Leatherman Terminal, the country’s first container terminal to open since 2009, is progressing toward a March 2021 opening. The site, situated on the former Navy Base along the Cooper River, is on track to become a world-class terminal. Following years of planning a

1 minutes read
  • LinkedIn
  • X
  • Email
Leatherman Terminal project on the home stretch
SCPA

Construction of SC Ports’ Hugh K. Leatherman Terminal, the country’s first container terminal to open since 2009, is progressing toward a March 2021 opening.

The site, situated on the former Navy Base along the Cooper River, is on track to become a world-class terminal.

Following years of planning and a complex construction process, the Leatherman Terminal will be ready to welcome container ships in less than six months.

Construction milestones

According to SCPA, a critical component of Phase One — the 1,400-foot wharf — is complete. The new facility will handle up to 19,000-TEU vessels with five of the tallest ship-to-shore cranes on the East Coast.

The overall site development of the Leatherman Terminal is approximately 75% complete.

As stated, SC Ports is in the final year of a six-year capital improvement plan, a culmination of years of strategic infrastructure planning and $2 billion in investments. The $1 billion Phase One of the Leatherman Terminal complements efforts to modernize Wando Welch Terminal and deepen Charleston Harbor to 52 feet.

These investments will enable SC Ports to handle four 14,000-TEU vessels simultaneously in 2021.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

InfrastructurePorts & Logistics

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free