DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Fawn Lake dredging plan on display
Infrastructure

July 16, 2020 · about 6 years ago

Fawn Lake dredging plan on display

The long-awaited Fawn Lake dredging project is scheduled to start in the following days, the Town of Bedford, Massachusetts, said in their latest announcement. The Town has contracted with Dredgit Corp. to dredge the pond and to reconstruct the outlet dam at Springs Road. The work includes hydraulic

1 minutes read
  • LinkedIn
  • X
  • Email
Fawn Lake dredging plan on display
Dredgit

The long-awaited Fawn Lake dredging project is scheduled to start in the following days, the Town of Bedford, Massachusetts, said in their latest announcement.

The Town has contracted with Dredgit Corp. to dredge the pond and to reconstruct the outlet dam at Springs Road.

The work includes hydraulic wet dredging of the bottom sediments to restore the lake to approximately 8-feet deep. The material is pumped from the dredge barge to a dewatering system.

Once the material is dried, it will be transported to a residuals holding area and then hauled off-site to a nearby compost facility for eventual reuse as loam.

Dredgit will utilize a small, portable dredge to hydraulically remove material from Fawn Lake.

The slurry from the lake will be pumped to a parallel array of multiple, high-capacity, big-bowl centrifuges for dewatering. The paint-filter-dry material will then be trucked to a local disposal facility.

The dam restoration and rehabilitation activities will proceed concurrently with the dredging and dewatering operations.

Phase I Mobilization – Initial Site Prep

Commencing on Tuesday, July 21, approximately four days (based on working 12-hours/day, 7-days/week) to prepare the material laydown holding area, including:

Phase II Mobilization – Equipment Set-up

Approximately four days to receive, install, and set up the dredging, dewatering, and material handling equipment, including:

Phase III Mobilization – Final Site Prep

Approximately four days to finish the material laydown holding area, including:

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Asia's largest TSHD begins Binhai Port dredging program
  2. 2Dominican Republic: The Netherlands, INTEC address climate change adaptation solutions
  3. 3CHEC builds breakwater at Apia Port on Samoa
  4. 4EXCLUSIVE: TSHD Teunis Huibertus gears up for Eemshaven job

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free