DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Improving Kent’s coastline
Infrastructure

June 22, 2020 · about 6 years ago

Improving Kent’s coastline

Works are underway to improve sea defenses along a 3.7km stretch of the Kent coastline between Hythe and Dymchurch, the beach frontage of a Ministry of Defence (MoD) firing range, said Mackley in their latest release. The Hythe Ranges Sea Defence project is being carried out by Van Oord working in p

1 minutes read
  • LinkedIn
  • X
  • Email
Improving Kent’s coastline
Image source: Mackley

The Hythe Ranges Sea Defence project is being carried out by Van Oord working in partnership with Mackley and on behalf of the Environment Agency.

A key element of the scheme is the refurbishment of timber groynes, with Mackley installing a total of 23 groynes – the longest of which is 104 metres – in two phases.

Phase one of the groyne refurbishment – which got underway in April and is now complete – saw Mackley install the first eight groynes and repair a number of others.

Phase two is now in progress, with the remainder of the groynes set to be refurbished by October.

One of the main aims of the project is to protect the Dymchurch Redoubt, a scheduled historic moment. The protection includes a new rock revetment and sheet piled wall, the company said.

In July, 38,000t of imported rock will be shipped to the site via a coaster, before being transferred to a barge for delivery to the foreshore.

The construction of a new steel sheet pile wall take place behind the existing seawall, in order to reinforce the structure, said Mackley.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free