DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Loyall slope repair wraps up
Infrastructure

June 10, 2020 · about 6 years ago

Loyall slope repair wraps up

The U.S. Army Corps of Engineers’ Nashville District has completed work to repair a slope above the Cumberland River diversion channel in Loyall, Kentucky. The Corps of Engineers awarded the $3,921,775 Loyall Slide Repair contract February 13, 2019 to Kay & Kay Contracting, LLC, in London, Kentucky.

1 minutes read
  • LinkedIn
  • X
  • Email
Loyall slope repair wraps up
USACE

The U.S. Army Corps of Engineers’ Nashville District has completed work to repair a slope above the Cumberland River diversion channel in Loyall, Kentucky.

The Corps of Engineers awarded the $3,921,775 Loyall Slide Repair contract February 13, 2019 to Kay & Kay Contracting, LLC, in London, Kentucky.

Michael Lee , Nashville District project manager, said that a lot of credit for completing the repair project on time and on budget goes to Mike Merida, contractor’s project manager; Zach Sewell, contractor’s superintendent; Allen Malcomb, Nashville District project engineer; and Joe Duncan, Nashville District quality assurance inspector; and Bruce Rogers, Nashville District geologist.

“We had to excavate the slide area from the top down in a series of lifts, stabilizing the exposed rock with rock bolts and geogrid (geosynthetic material, made of polymers, that is used to reinforce soil behind retaining walls),” Lee said “We placed engineered rock fill in a series of lifts against the excavated rock wall to provide a buttress for long-term stability.”

The contractor completed slope repair May 27, 2020.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free