DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Update on the Levee Works in the Kansas City District
Business & Finance

May 3, 2020 · about 6 years ago

Update on the Levee Works in the Kansas City District

The U.S. Army Corps of Engineers, Kansas City District has released an update on the progress made in their levee rehabilitation program. As reported, there are 66 levee systems on target for repairs, some with breeches, some with other surface damage such as grass kill or scour holes. The Corps cur

1 minutes read
  • LinkedIn
  • X
  • Email
Update on the Levee Works in the Kansas City District
Image source: USACE

The U.S. Army Corps of Engineers, Kansas City District has released an update on the progress made in their levee rehabilitation program.

As reported, there are 66 levee systems on target for repairs, some with breeches, some with other surface damage such as grass kill or scour holes.

The Corps currently has 24 contracts awarded with another 16 currently advertised for bids or pending award. Contractors have begun moving dirt on 8 of the 24 awarded contracts – this number is increasing daily.

USACE expects to advertise for construction all but five of the remaining contracts in the next two months, pending necessary project agreements. Most units have access agreements in place and project partnership agreements executed that is allowing construction to begin.

The five remaining systems requested assistance in December 2019 or in 2020. On these remaining units, engineers will complete the damage assessment stage in May followed by design and construction this summer, reported the Corps.

The original level of protection is in place or has been restored on 38 levees, while breaches remain to be repaired at 28 levees.

USACE anticipates that contractors will complete many of the rehabilitations this summer and fall with some needing to be finished in 2021.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free