DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Massey’s Ditch Dredging About to Begin
Business & Finance

January 10, 2020 · about 6 years ago

Massey’s Ditch Dredging About to Begin

J.F. Brennan Construction of La Crosse, Wisc., is ready to begin work on the 2020 Massey’s Ditch dredging project. Massey’s Ditch, an important navigation channel that runs between Rehoboth Bay and Indian River Bay, will be dredged starting this January. During the works, the waterway will be dredge

1 minutes read
  • LinkedIn
  • X
  • Email
Massey’s Ditch Dredging About to Begin

J.F. Brennan Construction of La Crosse, Wisc., is ready to begin work on the 2020 Massey’s Ditch dredging project.

Massey’s Ditch, an important navigation channel that runs between Rehoboth Bay and Indian River Bay, will be dredged starting this January.

During the works, the waterway will be dredged to a width of 100 feet and a depth of 7.5 feet below Mean Lower Low Water (MLLW).

The contractor will remove approximately 100,000 cubic yards of material from the channel and adjacent areas including the entrance to Baker’s Channel, on the north side of Lynch Thicket Island, and a large shoal between the south end of Lynch Thicket Island and Middle Island.

According to the Delaware Department of Natural Resources and Environmental Control, dredging is scheduled to begin in early January and will take approximately 31 days to complete the works.

The dredged material will be used to re-nourish the beach north of the inlet providing erosion and storm damage protection to the Route 1 bridge approach. It will also restore a heavily used public recreational beach area.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Willapa Harbor dredging underway
  2. 2Dredging begins on Gugu River in Pampanga
  3. 3Boskalis Nederland: Work on Fish Migration River Afsluitdijk in full swing
  4. 4New sand arrives at West Beach and Henley Beach South

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free