DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Additional $35.3 Million for the Jacksonville Harbor Deepening
Business & Finance

September 17, 2019 · about 7 years ago

Additional $35.3 Million for the Jacksonville Harbor Deepening

The Florida Department of Transportation (FDOT) has awarded JAXPORT an additional $35.3 million in funding for the Jacksonville Harbor Deepening project. The funding will be used toward exercising the second phase of U.S. Army Corps of Engineers’ contract B, which will deepen the project’s next 2.5

1 minutes read
  • LinkedIn
  • X
  • Email

The Florida Department of Transportation (FDOT) has awarded JAXPORT an additional $35.3 million in funding for the Jacksonville Harbor Deepening project.

The funding will be used toward exercising the second phase of U.S. Army Corps of Engineers’ contract B, which will deepen the project’s next 2.5 miles.

To date, the state of Florida has contributed nearly $71.5 million toward harbor deepening.

That funding, combined with significant financial support from the federal government and a private tenant, helps keep the project two years ahead of schedule with anticipated completion in 2023, based on continued funding from all partners.

The Jacksonville Harbor Deepening project is divided into four segments, contracts A-D, which make up the full length of the 13-mile federally authorized project. The current funding model covers the project’s first 11 miles (contracts A, B and C).

Contractors for the Army Corps are simultaneously working to complete contracts A and B, which will deepen a total of 8 miles. Contract A is scheduled to be complete in spring 2020, with contract B scheduled to conclude in May 2021.

Contract C will deepen an additional 3 miles to Blount Island and is entering the final design phase.

Deepening the Jacksonville shipping channel to 47 ft. will allow JAXPORT to accommodate more cargo aboard the larger ships currently calling Jacksonville from counties in Asia—including Japan, South Korea, China, Vietnam, Thailand and more.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1The largest annual dredging work on Great Lakes in full swing
  2. 2Pacific Dredge completes Port of San Diego dredging
  3. 3Ellicott delivers another Mud Cat to Canada
  4. 4Dredging work underway near Lancelin jetty

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free