DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Latest Update on the Exmouth Tidal Defense Scheme
Business & Finance

August 28, 2019 · about 7 years ago

Latest Update on the Exmouth Tidal Defense Scheme

The Environment Agency earlier today presented the latest update on the Exmouth tidal defense scheme. The EA reported that work continues on defense wall and revetment at Royal Avenue, piling and gabions at Camperdown Creek and improvements to the sea wall along the seaward side of the Esplanade. Th

1 minutes read
  • LinkedIn
  • X
  • Email

The Environment Agency earlier today presented the latest update on the Exmouth tidal defense scheme.

The EA reported that work continues on defense wall and revetment at Royal Avenue, piling and gabions at Camperdown Creek and improvements to the sea wall along the seaward side of the Esplanade.

They also added that in September, the work will start on secondary defenses and associated drainage on the north side of the Esplanade between the Grove and Premier Inn.

For some of the work to proceed, the road will need to be closed in sections between the Grove, along Morton Crescent, Alexandra Terrace Junction and past the Clock Tower up to the Premier Inn, announced the Environment Agency.

The Exmouth tidal defense scheme – being jointly undertaken by the Environment Agency and East Devon District Council – includes new flood walls, ground raising, flood gates and property flood resilience measures along the sea front and estuary-side.

Team Van Oord (TVO) were awarded the design and build contract for the Exmouth tidal defense scheme in October 2017.

The scheme is part of the Environment Agency’s program of £2.6 billion investment into flood defenses across the country.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1The largest annual dredging work on Great Lakes in full swing
  2. 2Pacific Dredge completes Port of San Diego dredging
  3. 3Ellicott delivers another Mud Cat to Canada
  4. 4Dredging work underway near Lancelin jetty

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free