DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Jackson Halfway Through the Clacton Scheme
Business & Finance

March 20, 2019 · about 7 years ago

Jackson Halfway Through the Clacton Scheme

Jackson is halfway though the Clacton Slope Stabilization Scheme aimed to prevent slipping occurring and make access to the lower promenade safer. The company is undertaking the £3.8 million slope stabilization works, installing a new access ramp to the sea front on the Clacton/Holland coast line, o

2 minutes read
  • LinkedIn
  • X
  • Email

Jackson is halfway though the Clacton Slope Stabilization Scheme aimed to prevent slipping occurring and make access to the lower promenade safer.

The company is undertaking the £3.8 million slope stabilization works, installing a new access ramp to the sea front on the Clacton/Holland coast line, on behalf of Tendring District Council.

According to Jackson, all piling activities have now been successfully installed. This consisted of 220 meters of king post piling within the embankment and 210 meters of sheet piling at the toe.

A specialist drainage scheme to take the groundwater from the slope down to the promenade is now underway.

To maintain stabilization, inclined slope drainage has been installed by a pioneering method called ‘directional drilling’ from the top of the cliff slope to the bottom.

This takes the groundwater into a specially built chamber on the promenade which will fall into the existing drainage system. A gravel filter drainage system is also being installed in front and behind the piled wall.

Recycled plastic enviro-chambers are being used on site to create the promenade manholes within the filter drainage system. Ordinarily these are constructed using concrete.

Works to construct a DDA (Disability Discrimination Act 2005) compliant footpath and access ramp is underway. This will benefit residents and visitors who are less mobile, and the ‘zig-zag’ design will make an attractive feature.

A walkway from Kings Avenue to the lower promenade will also be built – this very popular access point has been closed for many years due to the substantial cliff movement.

The works are due to complete in time for the summer season.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free