DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›McAmis Makes Good Progress with the North Jetty
Business & Finance

January 28, 2019 · about 7 years ago

McAmis Makes Good Progress with the North Jetty

J.E. McAmis crews have been working hard over the last couple of months making the Columbia River North Jetty Rehabilitation Project a dream come through. In an effort to rebuild the MCR North Jetty, the company is reshaping the existing jetty, extending it 250′ further into the Pacific. During the

1 minutes read
  • LinkedIn
  • X
  • Email

J.E. McAmis crews have been working hard over the last couple of months making the Columbia River North Jetty Rehabilitation Project a dream come through.

In an effort to rebuild the MCR North Jetty, the company is reshaping the existing jetty, extending it 250′ further into the Pacific.

During the length of the project, McAmis will place approx. 180,000 tons of stone ranging up to 40 tons each. The stones are being trucked in from domestic sources, as well as barged down 13,000 tons at a time, from a source in Canada.

According to the contractor, the stones in the stockpile range from around 10 tons up to 32 tons each. 130,000 tons of the 180,000 tons estimated to complete the North Jetty jetty is in staging or already placed.

The ongoing repairs are the second phase of the Army Corps’ plan to repair three jetties at the mouth of the Columbia River. USACE has already completed two years of work on the mile-long “A” Jetty at a cost of approx. $30 million.

Following the completion of the North Jetty scheme later this year, the Corps will begin stage three of the project, rehabilitating the six-mile-long South Jetty. The works will take place between 2019 and 2023.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free