DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Update on Church Scar Coastal Protection Scheme
Business & Finance

May 20, 2018 · about 8 years ago

Update on Church Scar Coastal Protection Scheme

The piling work at Church Scar is now complete, and the temporary road which is used to transport materials along the promenade has been created, reports the Flyde Council. According to the Council, the temporary road will allow a one way traffic system for the construction vehicles to transport mat

1 minutes read
  • LinkedIn
  • X
  • Email

The piling work at Church Scar is now complete, and the temporary road which is used to transport materials along the promenade has been created, reports the Flyde Council.

According to the Council, the temporary road will allow a one way traffic system for the construction vehicles to transport materials along the promenade.

“ The demolition of the existing sea defense wall for Phase 1 of the work at Church Scar is underway, and we will continue to remove this over the upcoming months, ” the Council said. “ The construction of the new sea defense wall at Church Scar has begun, and this will be topped with a thin layer of concrete.”

The layer of concrete will act as a bedding for the new concrete sea defense wall units, which we will then begin to place. The placement of the new units will take approximately 6 months to complete.

Th Church Scar Coastal Protection Scheme is a partnership between Fylde Council, VBA and the Environment Agency.

VBA, the main contractor, is a joint venture comprising VolkerStevin, Boskalis Westminster and SNC-Lavalin’s Atkins business, who specialize in designing and constructing sustainable flood and coastal defenses throughout the UK.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free