DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Four Bids Received for Nags Head Beach Renourishment
Business & Finance

March 19, 2018 · about 8 years ago

Four Bids Received for Nags Head Beach Renourishment

The Town of Nags Head reported last Friday that four bids have been received for the upcoming beach renourishment project. According to the town’s officials, the bids were submitted from Dutra Group, Great Lakes Dredge & Dock Company (GLDD), Manson Construction Company, and Weeks Marine. “Based on t

1 minutes read
  • LinkedIn
  • X
  • Email

The Town of Nags Head reported last Friday that four bids have been received for the upcoming beach renourishment project.

According to the town’s officials, the bids were submitted from Dutra Group, Great Lakes Dredge & Dock Company (GLDD), Manson Construction Company, and Weeks Marine.

“ Based on the bid items submitted by each bidder, the town’s beach nourishment engineering firm, Coastal Science & Engineering, Columbia, South Carolina, evaluated the bids by the total cost for placing 3.73 million cubic yards of sand on the beach, as well as the total cost of placing 4 million cubic yards of sand on the beach (the permitted maximum quantity), ” the town reported.

The total project costs for the Nags Head renourishment project are divided into the town’s portion of 2.3 MCY of beach fill placement or $25.5M total project budget and the FEMA restoration portion of 1.43 MCY beach fill placement or $16.2M project estimate.

Approximately 50% of the town’s total project budget will be funded for the Dare County Beach Nourishment Fund (~$12.5M).

The received bids will be presented to Nags Head’s Board of Commissioners at the April 4, 2018 meeting.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Boskalis: Geopolitical tensions in the Middle East adversely impact activity levels
  2. 2Anaklia dredging project accelerates with two Jan De Nul TSHDs in the area
  3. 3VIDEO: Damen TSHD Kapuka gears up for sea trials
  4. 4Spotlight on Tuvalu Coastal Adaptation Project in Funafuti

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free