Dover Western Docks Revival Latest Progress Update (VIDEO)

Business & Finance

Progress continues on the Dover Western Docks Revival (DWDR) development project, according to the latest video update on the works.

The scheme is the single biggest investment ever undertaken by the Port of Dover.

VSBW, the joint venture between Boskalis Westminster and VolkerStevin, was appointed in early 2017 as the main contractor for the marine engineering stage of the DWDR development.

Overall, the project includes the design and construction of two new berths including quay walls and land reclamation, a new marina pier, the marina curve, navigation channel and new lock gates, bascule bridge and capital dredging work.

According to the officials, the DWDR development project is moving right along with the timeline, with the phase one of the works scheduled to be completed at the end of 2018.