DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dredging Equipment Arrives in Port of Dover
Business & Finance

April 4, 2017 · about 9 years ago

Dredging Equipment Arrives in Port of Dover

Specialist vessels have started to arrive at the Port of Dover for the official start of harbor dredging for the port’s flagship Dover Western Docks Revival (DWDR) development scheme. The DWDR principal contractor, a joint venture between VolkerStevin and Boskalis Westminster (VSBW), has mobilized v

2 minutes read
  • LinkedIn
  • X
  • Email

Specialist vessels have started to arrive at the Port of Dover for the official start of harbor dredging for the port’s flagship Dover Western Docks Revival (DWDR) development scheme.

The DWDR principal contractor, a joint venture between VolkerStevin and Boskalis Westminster (VSBW), has mobilized various items of floating equipment which has begun arriving in Dover to undertake initial harbor dredging to remove soft sediment.

The first vessel to arrive was the ‘Kreeft’, a self-propelled crane barge which is fitted with bespoke attachments for the identification and removal of obstructions, VolkerStevin said in its latest release.

Dredging vessels include two trailing suction hopper dredgers, the 1,500m³ capacity ‘Sospan Dau’ and one of the 4,500m³ Causeway class vessels. These will dredge, remove and relocate soft sediment to the designated offshore licensed disposal area.

Harder material will be dredged with the ‘MP40’ backhoe dredger, which will transfer dredged material to the 800m³ self-discharging split hopper barges ‘Wadden 1’ and ‘Wadden 4’ for removal to the disposal area.

The trailer dredgers and split hoppers will be steaming regularly between the Port and the disposal area ahead of the initial piling program, VolkerStevin said.

Stuart Eckersley, Project Director for VSBW , said: “Starting the main dredging activities marks an important milestone for the project. We will be seeing a range of specialist vessels operating in the harbor from Boskalis Westminster’s extensive dredging fleet.”

Approximately one million cubic meters of silt, gravel and chalk will be removed from the harbor to allow for the creation of a purpose-built cargo and logistics facility, a new marina and a transformed waterfront at Europe’s busiest ferry Port.

[mappress mapid=”23866″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnologyVessels

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Van Oord's Rijn gears up for South-West India Dock Entrance job
  2. 2Manson nabs $17.3 million Belle Chasse dredging deal
  3. 3USACE wraps up McGregor Lake restoration project
  4. 4Mike Hooks wins Port Neches dredging contract

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free