DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›CMP Finishes Pontoon Berthing Facility for DONG
Business & Finance

November 16, 2014 · about 11 years ago

CMP Finishes Pontoon Berthing Facility for DONG

DONG recently awarded Commercial Marine and Piling Ltd. (CMP) a contract to construct & install a complete berthing system for the crew transfer vessels in Barrow in Furness. The contract included dredging, socketing piles into rock and construction of heavy concrete pontoons on site and the fabrica

1 minutes read
  • LinkedIn
  • X
  • Email

DONG recently awarded Commercial Marine and Piling Ltd. (CMP) a contract to construct & install a complete berthing system for the crew transfer vessels in Barrow in Furness.

The contract included dredging, socketing piles into rock and construction of heavy concrete pontoons on site and the fabrication and installation of steel access platform and bridge. The pontoon facility was regularly tested close to its maximum design conditions on a number of occasions between December and February 14th.

Wind gusts of 45 m/s (160 km/h) were recorded locally (12.2.14) and waves in excess of 1.2 meters approaching from the south have been observed at the pontoon berthing facility on a number of days.

On 3rd January 2014 the highest ever recorded water level was experienced at Barrow with a high tide of more than 11 meters bringing the water level close to the top of the quay edge and the decks of the pontoons close to 1 meter from the tops of the piles.

The pontoon and services facility performed as designed and without problems. They demonstrated to be a very safe and stable berthing facility for use by DONG vessels and personnel in all weather conditions.

[mappress mapid=”19263″]

Source: cmp

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free