DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Stevenson’s Creek Dredging Wrapped Up
Business & Finance

June 21, 2014 · about 12 years ago

USA: Stevenson’s Creek Dredging Wrapped Up

May 30, 2014, marked the end of a 6 month dredging project in Stevenson’s Creek, Clearwater, FL. Gator Dredging (the United States Army Corp of Engineers approved dredging contractor for Stevenson’s Creek) has successfully completed their hydraulic dredging project as part of the extensive effort to

1 minutes read
  • LinkedIn
  • X
  • Email

May 30, 2014, marked the end of a 6 month dredging project in Stevenson’s Creek, Clearwater, FL.

Gator Dredging (the United States Army Corp of Engineers approved dredging contractor for Stevenson’s Creek) has successfully completed their hydraulic dredging project as part of the extensive effort to enhance water quality and remove sediment build-up in the Stevenson’s Creek Estuary.

The project scope consisted of dredging of approximately 105,000 cubic yards of sediment from the canal. “Reach 1” called for the removal of 63,000 cubic yards of muck/sand material. This encompassed an area approximately 1,700 linear feet long, to a depth limit of -3.5 feet NGVD. “Reach 2” included the removal of an additional 42,000 cubic yards of muck/sand material for approximately 1900 linear feet, to a depth limit of -2.5 feet NGVD.

Gator Dredging successfully developed and executed USACE approved material management plan that processed the dredged material and transported the separated sediment to designated disposal sites. This process included placing dewatered muck material on an upland site located approximately 21 miles northeast of the project. The plan also called for the placement of clean, sandy material to be reused on location. This material created 15,488 square yards of mangrove habitat in Stevenson’s Creek Reaches 1 and 2.

Gator Dredging’s engineers developed, maintained, and restored the designated processing site and staging area located near the easterly limit of project.

[mappress]

Press Release, June 22, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free