DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Kovilic Construction Bags Sakonnet Breakwater Contract (USA)
Business & Finance

December 15, 2013 · about 12 years ago

Kovilic Construction Bags Sakonnet Breakwater Contract (USA)

The Sakonnet Harbor Breakwater in Little Compton, Rhode Island, will be repaired under the terms of a $594,500.00 contract issued recently by the U.S. Army Corps of Engineers, New England District. Work will be accomplished by Kovilic Construction Company, Inc., of Franklin Park, Ill. Construction i

2 minutes read
  • LinkedIn
  • X
  • Email

The Sakonnet Harbor Breakwater in Little Compton, Rhode Island, will be repaired under the terms of a $594,500.00 contract issued recently by the U.S. Army Corps of Engineers, New England District.

Work will be accomplished by Kovilic Construction Company, Inc., of Franklin Park, Ill. Construction is scheduled to start on or about Feb. 15, 2014 and take about three months to complete. The contract was awarded on Dec. 10, 2013.

The work for this project consists of repairing the breakwater, located on the west side of the Sakonnet Harbor in Little Compton. Repairs involve mobilization and demobilization, and the furnishment, delivery and placement of new stone to replace stones displaced during Hurricane Sandy in October 2012 and to fill in existing gaps and low points along the breakwater.

“The repairs will be performed to restore the damaged sections of the breakwater to the original profiles and cross-sections, ” said Project Manager Mike Walsh, of the Corps’ New England District, Programs/Project Management Division in Concord, Mass. “ Repairs will require substantial moving and manipulation of existing stones to obtain the required interlocking placement.”

The Sakonnet Harbor breakwater is an 800-foot-long stone structure with a crest height of 8.0 feet above mean low water, and a crest width of 15 feet. Mobilization of equipment and rehabilitation of the breakwater may require a combination of marine construction methods and resources.

The project will be managed by the Corps and all work will be accomplished under the supervision of a Corps’ Quality Assurance Representative to assure compliance with contract requirements.

[mappress]

Press Release, December 16, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Van Oord's dredger Utrecht returns to Itajaí
  2. 2Weeks Marine completes beach nourishment in Nags Head
  3. 3BREAKING NEWS: Pinglu Canal passes completion acceptance inspection
  4. 4Split hopper dredger Trud R busy at the Seaway

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free