DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›IADC: New “Facts About Early Contractor Involvement – Revisited” (The Netherlands)
Business & Finance

June 3, 2013 · about 13 years ago

IADC: New “Facts About Early Contractor Involvement – Revisited” (The Netherlands)

The preparatory work for large infrastructure projects often consumes an extraordinary amount of time, money and human resources and is not particularly cost-effective. Some of this inefficiency is caused by traditional procurement methods which bring contractors into the process after many key deci

2 minutes read
  • LinkedIn
  • X
  • Email

The preparatory work for large infrastructure projects often consumes an extraordinary amount of time, money and human resources and is not particularly cost-effective.

Some of this inefficiency is caused by traditional procurement methods which bring contractors into the process after many key decisions have been made. Often clients and consultants make design decisions with insufficient information and knowhow as to the available technology, equipment and potential innovative solutions. The contractors may be challenged because of insufficient knowledge of the physical conditions at the project site.

Early Contractor Involvement (ECI) provides an efficient means of designing and planning infrastructure projects in a cost-effective, more efficient and less adversarial structure.

Using ECI with a properly executed contract that reflects a relationship able to deal with project risks should increase transparency and therefore reduce risks, increase shared responsibilities and limit the reasons for disputes.

With traditional procurement a client/owner must make many decisions before accurate information has been collected. The experiential knowledge of contractors is rarely requested in the planning stages and is therefore seldom used. This ultimately leads to inaccurate conclusions, which may have an adverse effect on the project outcome in terms of price, time and quality.

Project designers – who do not necessarily know how to scope and cost – come on board first. Thereafter contractors brought in. Getting involved when a design has already been determined forces contractors to be re-active instead of pro-active. By telling the contractor what to do, by taking the lowest price and negotiating it downwards, project risks increase. Rather than negotiating the price downwards, prices and the risk of poor performance rise.

Frequently when project performance on an infrastructure project is less than optimal, the reputation of the construction industry in general is harmed: The public’s perception (and the client’s) may be that time schedules are not trustworthy, budgets will run wild, technical solutions are failing and the government, the authority and the industry seem to have difficulty getting it right.

More info

[mappress]

Press Release, June 4, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free