DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Folly Beach Post-Sandy Assessment Complete
Business & Finance

November 6, 2012 · about 14 years ago

USA: Folly Beach Post-Sandy Assessment Complete

Upon completion of a post-storm assessment after the effects of Superstorm Sandy, the Charleston District has determined that the estimated sand loss to the federal project at Folly Beach is approximately 75,000-100,000 cubic yards. In order to restore Folly Beach to pre-Sandy conditions, the Distri

2 minutes read
  • LinkedIn
  • X
  • Email

Upon completion of a post-storm assessment after the effects of Superstorm Sandy, the Charleston District has determined that the estimated sand loss to the federal project at Folly Beach is approximately 75,000-100,000 cubic yards.

In order to restore Folly Beach to pre-Sandy conditions, the District estimates that it would cost $2.7-3.5 million to replace the lost sand. In comparison, Hurricane Irene caused an estimated 300,000-350,000 cubic yards of lost sand at Folly Beach.

Approximately $1.4 million would be for the mobilization/demobilization of the dredge alone. The District’s estimates only account for sand loss to the federal project and do not include sand loss beyond the line of the project. Based on photographs and inspection of the beach, there was some sand loss beyond the line of the project and some structures that sustained erosion damage, but the Charleston District does not calculate these damages as these damage assessments are the responsibility of the City of Folly Beach.

The Charleston District has completed their assessment and provided the required information to Corps of Engineers headquarters in Washington, D.C. Should a disaster declaration be made for areas within the state of South Carolina and should funding from a supplemental appropriations bill become available, the Charleston District will work with the City of Folly Beach to work through the process to determine if the impacts meet the criteria to allow the project to be restored to pre-Sandy conditions.

The federal project at Folly Beach reached the trigger point for regular renourishment prior to Superstorm Sandy. At this time, the Charleston District has received $400,000 for the federal project to complete plans and speculations and environmental assessments. The FY14 President’s Budget, to be released in February, will determine if the project receives additional funding for renourishment of the beach.

[mappress]

Press Release, November 7, 2012

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free