DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Army Corps Begins Orleans Parish Drainage Project
Business & Finance

September 10, 2012 · about 14 years ago

USA: Army Corps Begins Orleans Parish Drainage Project

The U.S. Army Corps of Engineers, New Orleans District recently began construction on a 46-month contract to provide increased drainage for the Carrollton area through drainage canal improvements along South Claiborne Avenue between Leonidas and Lowerline Streets. Tree removal work required for the

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, New Orleans District recently began construction on a 46-month contract to provide increased drainage for the Carrollton area through drainage canal improvements along South Claiborne Avenue between Leonidas and Lowerline Streets.

Tree removal work required for the project will start Monday, September 10, 2012. The “Claiborne Ave – Phase Two” project, which is part of the Southeast Louisiana Urban Flood Damage Reduction Project (SELA), will reduce the risk of damages from a rainfall event that has a chance of occurring once in every ten years.

The $27.8 million contract calls for the Louisiana-based B&K Construction Co, LLC to construct approximately 3,400 feet of covered drainage canal, as well as the relocation of minor electrical and water line to accommodate the project. The “Claiborne Ave – Phase Two” project area is noted on the below map.

In order to facilitate construction, the Claiborne Avenue neutral ground area will require clearing from Cambronne to Pine Streets. Necessary tree removal actions have been coordinated with the Corps’ partner, the Sewerage and Water Board of New Orleans, as well as the City of New Orleans’ Parks and Parkways department. A licensed arborist was hired to clear the neutral ground of all trees and shrubs in this area. Soon after the project is complete in the spring of 2016, landscaping will be restored in this area. The Corps will coordinate with the city of New Orleans and interested residents in developing a landscape design.

The Corps will continue to work closely with its partners at the Louisiana Coastal Protection and Restoration Authority and the Sewerage and Water Board of New Orleans on the SELA program. To date, a total of fourteen SELA contracts have been awarded in Orleans Parish, with work completed on 9 of those projects. All scheduled SELA work in Orleans Parish should be finished in 2017.

[mappress]

Press Release, September 10, 2012

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Charlotte Amalie dredging starts next month
  2. 2Dredger picks up 150 kg German bomb off Belgian coast
  3. 3GLDD wins South Atlantic Regional Harbor Dredging Contract
  4. 4Meaford Harbor in-water dredging completes

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free