DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›Australia: Progress on Bund Wall Project at Fisherman’s Landing on Schedule
News

July 5, 2012 · about 14 years ago

Australia: Progress on Bund Wall Project at Fisherman’s Landing on Schedule

Progress on the sealing of the northern section of the front bund wall at Fisherman’s Landing is on schedule. The 8.8km bund wall created to reclaim 274 hectares at the northern end the current Fisherman’s Landing site was completed in August 2011, since then 4 million cubic metres of dredge materia

2 minutes read
  • LinkedIn
  • X
  • Email

Progress on the sealing of the northern section of the front bund wall at Fisherman’s Landing is on schedule.

The 8.8km bund wall created to reclaim 274 hectares at the northern end the current Fisherman’s Landing site was completed in August 2011, since then 4 million cubic metres of dredge material have been stored inside the wall.

The material is pumped into the reclamation area using cutter suction dredges and sinkerlines.

The Transitional Environmental Program (TEP) approved on 25th June allows for bund sealing works to be undertaken until the 6th August to seal the northern section of the front bund wall of the reclamation area at Fisherman’s Landing.

The TEP is scheduled to seal the 900 metre section of the front bund wall to a 50 metre width using dredge material.

Since the TEP was actioned approximately 180,000 cubic metres of dredge material has been placed on the inside of the front bund wall.

Two cutter suction dredges have been operating under the TEP since the 28 June. There remains approximately 400 metres of the bund still to cover.

“ Sealing the north bund wall under the TEP is a strategy to reduce the impacts on the environment, ” GPC CEO Leo Zussino said.

“We are conducting the sealing process now as this is the dormant period for our seagrass beds and the impacts of this dredging will be minimal on these seagrass beds.”

The growing season for seagrass beds begins around July/August depending on ambient conditions.

GPC will update the community each week on the progress of the TEP.

[mappress]

Dredging Today Staff, July 6, 2012; Image: westernbasinportdevelopment

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free