DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›USA: Great Lakes Dredge & Dock Wins Port Manatee Berth 12 Dredging Bid
News

July 27, 2010 · about 16 years ago

USA: Great Lakes Dredge & Dock Wins Port Manatee Berth 12 Dredging Bid

The Manatee County Port Authority announced today that Great Lakes Dredge & Dock Co. has been awarded the contract for Port Manatee’s Berth 12 dredging project. The project, which includes dredging the berth to a depth of 41 feet at mean-low-water and extending it from 1,000 feet to nearly 1,600 fee

1 minutes read
  • LinkedIn
  • X
  • Email

The Manatee County Port Authority announced today that Great Lakes Dredge & Dock Co. has been awarded the contract for Port Manatee’s Berth 12 dredging project.

The project, which includes dredging the berth to a depth of 41 feet at mean-low-water and extending it from 1,000 feet to nearly 1,600 feet, is the final piece of Port Manatee’s 11-year, $200 million port expansion project.

Great Lakes’ $14.8 million bid was accepted just two months after initial bids were rejected by the port authority for exceeding the engineer’s estimate for the cost of the project. The re-bid process resulted in a $2.3 million savings for the port – 14 percent less than the original bid. The winning proposal includes the base bid and bid alternate, representing 1.1 million cubic yards of excavation and removal by hydraulic dredge to a certified uplands spoil disposal site.

“Port staff’s many years in dealing with dredging issues made us confident that a more favorable outcome was probable by re-bidding the project,” said David L. McDonald PPM®, Port Manatee’s executive director. “The savings provided by the lower bid creates a more certain timeline for the project’s completion.”

Port Manatee’s new Berth 12 is expected to accommodate containerized shipping and be operational by early-2011. The berth sits adjacent to the port’s planned 52-acre container terminal – designed to attract new containerized shipping traffic.

( businesswire )

[mappress]

Source: businesswire, July 28, 2010;

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Van Oord's dredger Utrecht returns to Itajaí
  2. 2Weeks Marine completes beach nourishment in Nags Head
  3. 3BREAKING NEWS: Pinglu Canal passes completion acceptance inspection
  4. 4Split hopper dredger Trud R busy at the Seaway

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free