DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›Work progresses on the Sebastian Inlet dredging and beachfill project
Beach Nourishment

January 31, 2025 · about 1 year ago

Work progresses on the Sebastian Inlet dredging and beachfill project

The Sebastian Inlet District (FL) has released the latest update about the ongoing dredging and beach nourishment project. According to the District, ATL Diversified (ATL) has completed about 20 percent of the Upland Truck Hauling and Beach Placement phase of the project (based on volume). During th

1 minutes read
  • LinkedIn
  • X
  • Email
Work progresses on the Sebastian Inlet dredging and beachfill project

Share this article

The Sebastian Inlet District (FL) has released the latest update about the ongoing dredging and beach nourishment project.

According to the District, ATL Diversified (ATL) has completed about 20 percent of the Upland Truck Hauling and Beach Placement phase of the project (based on volume).

During this phase, ATL is placing approximately 80,000 cubic yards of material on part of a 2.5-mile stretch of beach south of Sebastian Inlet.

ATL has also begun mobilizing its dredge in anticipation of the dredging portion of the project, which will likely begin in about two weeks.

When the project is completed by April 30, ATL will have hydraulically dredged approximately 215,000 cubic yards of beach-compatible sand from a designated sand trap and adjacent navigation channel located within Sebastian Inlet.

Sand will be placed on the downdrift beaches. This is in addition to the 80,000 cubic yards of beach-compatible sand currently being trucked in from an upland sand source.

The project is necessary for the Sebastian Inlet District to meet its requirement to bypass sand that migrates into the inlet system to downdrift beaches per the Florida Beach & Shore Preservation Act.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach NourishmentDredging

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Swiss Army Knife of Great Lakes in Ashtabula
  2. 2Puerto de Sevilla completes Guadalquivir dredging
  3. 3McLaughlin & Harvey appointed to Dover' Project Contractor Framework
  4. 4Oceanside Harbor dredging wraps up

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free