DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›North Wildwood emergency beach nourishment about to begin
Beach Nourishment

May 21, 2024 · about 2 years ago

North Wildwood emergency beach nourishment about to begin

The city of North Wildwood released new details yesterday about when an emergency project will begin to replenish its beaches. The city said that the emergency beach nourishment dredging project is expected to begin in the next 7 to 10 days and be completed by the July 4 holiday. Project preparation

1 minutes read
  • LinkedIn
  • X
  • Email
North Wildwood emergency beach nourishment about to begin

Share this article

The city of North Wildwood released new details yesterday about when an emergency project will begin to replenish its beaches.

The city said that the emergency beach nourishment dredging project is expected to begin in the next 7 to 10 days and be completed by the July 4 holiday.

Project preparation is underway and H&L Contracting and Great Lakes Dredge and Dock (GLDD), the contractor and sub-contractor for the NJDOT, are expected to begin mobilizing equipment this week.

According to the city, a dredge in the ocean will essentially pump out sand and push it out through a large pipe, which will discharge thousands of cubic yards of sand onto the beach.

The contractors currently intend to pump sand on the beach at 7th Avenue, proceeding South to North, wrapping around the jetty at 2nd Avenue and John F. Kennedy Blvd.

Once this section is complete, it is expected that the contractor will return to 7th Avenue, continuing south.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach Nourishment

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Dredging Africa presents new CSD
  2. 2Premier Marinas submits Brighton dredging application
  3. 3Dredging underway at Everett Harbor and Snohomish River
  4. 4PD Ports opens new Marine facility

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free