DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business development›Gosport Marina dredging in full swing
Business development

November 6, 2020 · about 5 years ago

Gosport Marina dredging in full swing

External contractor, ML Dredging is making good progress with the Gosport Marina 2020 dredging programme. The company started the Gosport campaign on September 28, 2020. The work is taking place 24/7 for approximately 8 weeks until mid-November. For this project, ML Dredging is using their backhoe d

1 minutes read
  • LinkedIn
  • X
  • Email
Gosport Marina dredging in full swing
Gosport Marina

External contractor, ML Dredging is making good progress with the Gosport Marina 2020 dredging programme.

The company started the Gosport campaign on September 28, 2020. The work is taking place 24/7 for approximately 8 weeks until mid-November.

For this project, ML Dredging is using their backhoe dredger, the “Witton II”. Barge “Split Three” is taking the dredged material for disposal to the Nab Tower disposal site.

According to Gosport Marina, the contractor is moving forward with this dredging project, which aims to remove a total of 25,000m3 of silt and mud. This will ensure deep water draft sailing and fully navigable waters continue within the marina for the berth holders.

They also added that the alternative entrance/exit at the floating breakwater has now been created and is fully lit and navigable to allow berth holders access into the marina.

“The works will be completed within the next two weeks, weather permitting,” said Jonathan Walcroft CMM, Marina Manager.

Once complete, the new depths will benefit both marina and their customers over a significant area of the marina.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business developmentOperations & Maintenance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Jan De Nul's TSHD Diogo Cão raises the bar in Vlissingen
  2. 2Skanska builds new homeport pier at Naval Station Newport
  3. 3Ecocoast, Xylem partnership strengthens turbidity monitoring for GCC dredging projects
  4. 4Seaward Marine wins $15.2M Virginia Beach contract

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free