DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Jimmys Beach replenishment works start
Infrastructure

August 5, 2020 · about 6 years ago

Jimmys Beach replenishment works start

MidCoast Council contractors are half way through dredging the eastern channel of the lower Myall River, with 60,000 cubic metres of sand added to the Winda Woppa stockpile so far. While the series of storm events through June and July slowed operations on certain days, the team had been pushing har

2 minutes read
  • LinkedIn
  • X
  • Email
Jimmys Beach replenishment works start
MidCoast Council

MidCoast Council contractors are half way through dredging the eastern channel of the lower Myall River, with 60,000 cubic metres of sand added to the Winda Woppa stockpile so far.

While the series of storm events through June and July slowed operations on certain days, the team had been pushing hard during finer conditions to ensure they remain on schedule and the navigation channel progresses as expected.

“Optimum conditions has allowed Dredging Solutions to dredge above targets during the early period of the campaign and to ease off when the adverse weather set in,” explained Andrew Staniland , MidCoast Council’s Coastal Management Coordinator.

“Another bonus of this project, and certainly a timely one given current conditions, is the ability to replenish Jimmys Beach using the dredge and as locals will understand, we need this right now.”

Council had originally intended to start moving sand onto Jimmys Beach in September – this has been brought forward to combat the significant erosion sustained over the last few weeks.

“The pipe work and booster pumps for this part of the operation were mobilised over the weekend and the team began pumping 20,000m3 onto the beach this week.

“Jimmys Beach is a vulnerable location and we know we need to move quickly given the damage that was sustained by the storms so I’m pleased we’ve been able to bring it forward to get a small buffer in place ready for the next storm,” added Andrew.

The dredged sand will target the section of beach between Guya Street and Kururma Crescent and will complement future sand placement projects by the Sand Transfer System.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Skanska builds new homeport pier at Naval Station Newport
  2. 2Ecocoast, Xylem partnership strengthens turbidity monitoring for GCC dredging projects
  3. 3Seaward Marine wins $15.2M Virginia Beach contract
  4. 4BREAKING NEWS: Renewed Afsluitdijk opens, Van Oord says

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free