DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Picayune Strand Restoration Project up for Comment
Business & Finance

May 15, 2020 · about 6 years ago

Picayune Strand Restoration Project up for Comment

The U.S. Army Corps of Engineers, Jacksonville District has opened public comment on the Draft Environmental Assessment (EA) and Proposed Finding of No Significant Impact (FONSI) regarding construction of features of the Picayune Strand Restoration Project (PSRP). The PSRP Draft EA and Proposed FONS

1 minutes read
  • LinkedIn
  • X
  • Email
Picayune Strand Restoration Project up for Comment

The U.S. Army Corps of Engineers, Jacksonville District has opened public comment on the Draft Environmental Assessment (EA) and Proposed Finding of No Significant Impact (FONSI) regarding construction of features of the Picayune Strand Restoration Project (PSRP).

The PSRP Draft EA and Proposed FONSI addresses the construction of design refinements for the Southwest Protection Feature (SWPF) levee with additional conveyance features, and the partial plugging of the Faka Union Canal, which is a change in sequence from the original authorization.

These refinements will provide continued flood risk reduction while increasing freshwater deliveries to downstream estuaries.

The Southwest Protection Feature levee, which will provide continued flood risk reduction for the agricultural lands southwest of the PSRP, must be constructed prior to the plugging of the remainder of the Faka Union Canal, Miller Canal, and Western Stair Step Canal, where most of the project benefits will be realized.

The Corps plans to proceed with award of the construction contracts for both the SWPF levee and conveyance features for the PSRP in late September 2020.

Due to the size and complexity of this project, implementation and construction has been phased throughout multiple years.

The Draft EA and proposed FONSI for regarding construction of features of the Picayune Strand Restoration Project are available for review at USACE website .

The deadline for sending comments on the proposed works is June 12, 2020.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free