DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›San Jacinto River Dredging Forecasted to Double
Business & Finance

June 19, 2018 · about 8 years ago

San Jacinto River Dredging Forecasted to Double

The U.S. Army Corps of Engineers officials extended bid invitations until June 22, 2018 after forecasted dredging material calculations increased for a FEMA funded emergency dredging operation of the West Fork of the San Jacinto River. “We’ve encouraged bidders to submit questions and this allowed u

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers officials extended bid invitations until June 22, 2018 after forecasted dredging material calculations increased for a FEMA funded emergency dredging operation of the West Fork of the San Jacinto River.

“ We’ve encouraged bidders to submit questions and this allowed us to revise dredging quantities ,” said Gary Stangeland, Interim Chief of Emergency Management at USACE Galveston District . “ We were able to recalculate the volume of material needed and therefore extended the bid opening and project finish date .”

Invitations to bid were to be opened yesterday but after contractors questioned the water surface elevations project drawings (plans), new calculations determined the volume of dredged material more than doubled.

Forecasted dredged material increased from 748,000 to 1.8 million cubic yards of material that has shoaled in areas of the West Fork of the San Jacinto River.

In addition, the duration of the project was extended from 180 days to 270 days to allow the winning contractor additional time to remove the increase in material.

“ Our process is equitable and efficient as it allows for Corps’ Engineers to interact with vendors that will help us to restore the area to pre-Harvey conditions and help reduce future flooding risks, ” said Jeff Neill, USACE Galveston District Contracting Chief. “ We’ve publicly posted responses to bidders’ questions to www.projnet.org .”

The scope of the emergency dredging did not change with no additional placement areas needed. Stangeland added that the two placement areas are sufficient to store the recalculated increase in forecasted dredged material.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Anaklia dredging project accelerates with two Jan De Nul TSHDs in the area
  2. 2VIDEO: Damen TSHD Kapuka gears up for sea trials
  3. 3Spotlight on Tuvalu Coastal Adaptation Project in Funafuti
  4. 4USACE starts feasibility study for Cooper River deepening

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free