DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Lake Decatur Dredging to Finish Ahead of Schedule
Business & Finance

November 24, 2017 · about 9 years ago

Lake Decatur Dredging to Finish Ahead of Schedule

Crews with Great Lakes Dredge and Dock are making good progress with the removal of sediment from the bottom of Lake Decatur. According to Matt Newell, interim director of the Decatur Public Works Department, the works are progressing well in Basin 3, between U.S. 36 and East William Street Road, an

2 minutes read
  • LinkedIn
  • X
  • Email

Crews with Great Lakes Dredge and Dock are making good progress with the removal of sediment from the bottom of Lake Decatur.

According to Matt Newell, interim director of the Decatur Public Works Department , the works are progressing well in Basin 3, between U.S. 36 and East William Street Road, and will shut down for the year before Christmas.

The work is to resume next spring, when GLDD will be finishing dredging of Basin 3 and begin work in Basin 4, located north of William Street Road.

Newell also added that as of mid-November around 76 percent of the work is complete, saying that with this pace the whole dredging project could be finished by the end of next year.

“ The dredging contractor is anticipating and is hopeful they can be done by next year ,” he said. Originally, this $91 million worth project was scheduled for completion in December 2019.

Lake Decatur was constructed on the Sangamon River as a public water supply reservoir in 1920-1923. Since then natural and human caused erosion severely reduced the lake’s storage capacity.

The lake is separated by bridges into six large basins. Basin 5 was reclaimed by dredging in 1993-1994 and Basin 6 in 2004-2011. The dredging of Basins 1 through 4 began in 2014 and will continue through 2018.

Once finished, the project will increase the lake’s storage capacity by 30% or 52 days of additional water supply for the community.

[mappress mapid=”24636″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE modernizes national dredging delivery through enterprise execution
  2. 2Dredging plan for Cedar River Harbor on the table
  3. 3BREAKING NEWS: Keyfield takes delivery of TSHD Inai Kenanga
  4. 4Work progresses on Grand Isle breakwaters

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free