DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GLDD Pushes on with Duck Beach Nourishment Project
Business & Finance

June 14, 2017 · about 9 years ago

GLDD Pushes on with Duck Beach Nourishment Project

A public meeting was held yesterday, June 14, in the Paul F. Keller Meeting Hall where Coastal Planning and Engineering and Great Lakes Dredge and Dock (GLDD) presented an update on the Town of Duck Beach Nourishment project. During the meeting, Julien Devisse, with Coastal Planning and Engineering,

1 minutes read
  • LinkedIn
  • X
  • Email

A public meeting was held yesterday, June 14, in the Paul F. Keller Meeting Hall where Coastal Planning and Engineering and Great Lakes Dredge and Dock (GLDD) presented an update on the Town of Duck Beach Nourishment project.

During the meeting, Julien Devisse, with Coastal Planning and Engineering, presented on the progress to date, as well as a tentative schedule.

According to the town, the Dodge and Padre Island dredges are currently finishing up working south from the Ocean Bay Blvd subline.

GLDD anticipates that they should be completed by tomorrow. They will then resume work at the Dianne St. subline and pump north to meet the completed beach.

At this time, the active construction zone for this area is between approximately Sea Tern Dr. and Carroll Dr.

The third dredge, the Liberty Island dredge has approximately 500 feet of beach left to complete to the southern boundary.

It is anticipated that this will be completed by this coming weekend and then return to Widgeon St. to work north until subline in Kill Devil Hills is ready to begin work.

Currently, the active construction zone is approximately Spyglass Rd and Spindrift Ln.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Bahrain plans major land reclamation at Khalifa Port
  2. 2Precision dredging at Newton Ferrers by TMS
  3. 3Two months to go: get your ticket for OEEC 2026
  4. 4PHOTO OF THE DAY: Dredge Potter returns for 2026 dredging season

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free