DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dredge B.E. Lindholm Kicks Off Ortley Beach Replenishment Project
Business & Finance

May 29, 2017 · about 9 years ago

Dredge B.E. Lindholm Kicks Off Ortley Beach Replenishment Project

Weeks Marine, Inc. dredge, the B.E. Lindholm, has begun works on the Ocean County storm damage reduction project in Toms River. The dredger arrived on Sunday, and after a day of preparations and setting up, started the Ortley Beach and Dune Replenishment project. According to local media, it took si

1 minutes read
  • LinkedIn
  • X
  • Email

Weeks Marine, Inc. dredge, the B.E. Lindholm, has begun works on the Ocean County storm damage reduction project in Toms River.

The dredger arrived on Sunday, and after a day of preparations and setting up, started the Ortley Beach and Dune Replenishment project.

According to local media, it took six days for the 297-foot hopper dredge to arrive from Tampa, where it was receiving maintenance repairs after its last assignment in Florida.

Ortley Beach, which sustained catastrophic property damage from Superstorm Sandy, will over the next two weeks receive over 267,000 cubic yards of sand, creating an approximately 225-foot-wide beach.

However, contrary to what the contractor originally proposed; the project will start working toward the south first, so that there will be more working room to transport equipment to and from the staging area near the Seaside border.

The Township of Toms River reported that the closure of the beach will still be limited to 1,000 feet at a time, and sand ramps will be provided over the pipe where it crosses the open beach areas.

[mappress mapid=”24125″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & TendersVessels

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Bahrain plans major land reclamation at Khalifa Port
  2. 2Precision dredging at Newton Ferrers by TMS
  3. 3Two months to go: get your ticket for OEEC 2026
  4. 4PHOTO OF THE DAY: Dredge Potter returns for 2026 dredging season

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free