DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Alexandra Dock Project on Track for Early 2017 Completion
Business & Finance

December 29, 2015 · about 10 years ago

Alexandra Dock Project on Track for Early 2017 Completion

Construction work on the Green Port Hull Alexandra Dock site is progressing well and is on schedule for an early 2017 completion, Associated British Ports (ABP) has announced. The 54-acre site, which ABP and its main contractor GRAHAM Lagan Construction Group Joint Venture (JV) are preparing for Sie

1 minutes read
  • LinkedIn
  • X
  • Email

Construction work on the Green Port Hull Alexandra Dock site is progressing well and is on schedule for an early 2017 completion, Associated British Ports (ABP) has announced.

The 54-acre site, which ABP and its main contractor GRAHAM Lagan Construction Group Joint Venture (JV) are preparing for Siemens’ offshore wind turbine manufacturing facility, is being transformed in Hull’s biggest engineering project since the port was built.

The enabling works undertaken by ABP and their contractors are worth £150 million.

The dock infill has now been completed, with one million cubic meters of sand pumped into the dock to fill one third of the water area.

Excess sand was stored during this process to be used for the 7.5 hectare reclaim, which will become the new quayside and component storage areas, and this is now being pumped into position around the existing timber sheds and jetties, which will be demolished in the coming weeks.

Marine piling for the new quay wall is almost complete and piling for the anchor wall and roll on-roll off ramp is continuing.

The JV has now taken control of the east side of the site to begin preparatory works for the 25,000 square meter service building. Five substations, which will supply 6MVA to the site, are also being built to supply the new facility with electricity.

[mappress mapid=”21742″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Kazakhstan, Jan De Nul discusses cooperation perspectives, spotlight on dredging
  2. 2Greatham North East flood alleviation scheme gets OK
  3. 3Gator Dredging nabs Banana River dredging deal
  4. 4EXCLUSIVE: Doca dos Bacalhoeiros dredging kicks off

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free