DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Panama Canal Project Enters Final Phase
Business & Finance

September 7, 2015 · about 11 years ago

Panama Canal Project Enters Final Phase

Earlier in June, the filling of the new locks began, marking the start of a planned and methodical phase of operational testing of the Locks, including its culvert valves, maintenance bulkheads and gates. This stage of testing is meant to timely detect and correct any deficiencies in the project. Th

2 minutes read
  • LinkedIn
  • X
  • Email

Earlier in June, the filling of the new locks began, marking the start of a planned and methodical phase of operational testing of the Locks, including its culvert valves, maintenance bulkheads and gates.

This stage of testing is meant to timely detect and correct any deficiencies in the project. The Panama Canal technical team is closely involved to ensure that all tests meet the quality standards established in the contract.

As part of this testing, some water seepage was detected in a specific area of the new Pacific Locks in a section that separates the middle chamber and lower chamber, as they were being stressed tested through exposure to level differentials much higher than those required for normal operations, but that may occur during dry-chamber maintenance works in the future.

The ACP is now awaiting a formal report from GUPC following detailed inspections. The report, will be inclusive of the root cause analysis conducted, as well as the recommended repair methodology. Upon evaluating the report’s findings, the ACP will assess and communicate if the project’s completion timeline will be altered in any way.

At this time, ACP has designated two independent external structural engineers to conduct an objective evaluation of the reasons for this localized issue and assess GUPC’s solution.

While this important step takes place, the ACP is encouraged by the overall progress of the program, which has now reached 93 percent completion. Parallel work presses ahead with testing in other areas; the removal of the strip of land – known as a ‘plug’- separating the new Cocolí Locks from the Pacific Ocean, and the culmination of the Pacific Access Channel work.

Likewise last week the removal of the dike or plug that separates the Atlantic ocean waters from the new Atlantic Lock was initiated and progresses at a good pace.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Conneaut Harbor dredging kicks off
  2. 2BREAKING NEWS: Bahrain plans major land reclamation at Khalifa Port
  3. 3Precision dredging at Newton Ferrers by TMS
  4. 4Two months to go: get your ticket for OEEC 2026

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free