DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›LPC’s Cashin Quay 2 Completed
Business & Finance

March 8, 2015 · about 11 years ago

LPC’s Cashin Quay 2 Completed

Reconstruction of the first 57 meter section of the Lyttelton Port of Christchurch (LPC) Cashin Quay 2 wharf has been completed, providing a second container vessel berth at the wharf for the first time since the February 2011 earthquake. The rebuilding of Cashin Quay 2, following earthquake damage,

1 minutes read
  • LinkedIn
  • X
  • Email

Reconstruction of the first 57 meter section of the Lyttelton Port of Christchurch (LPC) Cashin Quay 2 wharf has been completed, providing a second container vessel berth at the wharf for the first time since the February 2011 earthquake.

The rebuilding of Cashin Quay 2, following earthquake damage, is being delivered in stages. By late April the new wharf should reach 101 meters. The entire 230 meter long wharf will be completed by the end of the year.

“ The new Cashin Quay 2 wharf is an important part of planning effectively for future growth and customer service ,” said LPC Chief Executive Peter Davie . “ It will be a development milestone, increasing capacity for the Container Terminal, boosting the number of berths available and providing increased operational efficiency for customers. ”

An important part of the construction project has been driving more than 255 piles into the seabed and tying them to the wharf with steel anchor rods. This anchor system gives a high level of seismic resilience, providing a stronger structure than the previous wharf.

The main pile driving of 70 meter piles will be completed this month, while driving the smaller 12 meter long piles by the end of July.

[mappress mapid=”20075″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Precision dredging at Newton Ferrers by TMS
  2. 2Two months to go: get your ticket for OEEC 2026
  3. 3PHOTO OF THE DAY: Dredge Potter returns for 2026 dredging season
  4. 4VIDEO: Spotlight on $642M Oakland Harbor turning basins widening

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free