DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Goodloe Marine to Dredge Gulf Intracoastal Waterway
Business & Finance

April 12, 2014 · about 12 years ago

USA: Goodloe Marine to Dredge Gulf Intracoastal Waterway

The U.S. Army Corps of Engineers, Galveston District, awarded a contract in the amount of $6,318,000 to Goodloe Marine Inc. to perform maintenance dredging within the Gulf Intracoastal Waterway, between Turnstake Island and Live Oak Point, in Calhoun, Aransas and San Patricio counties, Texas. The co

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Galveston District, awarded a contract in the amount of $6,318,000 to Goodloe Marine Inc. to perform maintenance dredging within the Gulf Intracoastal Waterway, between Turnstake Island and Live Oak Point, in Calhoun, Aransas and San Patricio counties, Texas.

The contractor is required to remove approximately 1.6 million cubic yards of shoaled material from the channel reaches to provide sufficient channel depth for the transit of shallow-draft vessels. The dredge material will be placed in open water and upland placement areas directly adjacent to the Gulf Intracoastal Waterway.

“ Execution of this maintenance dredging contract is critical to providing unrestricted navigation along this portion of the Gulf Intracoastal Waterway ,” said Chris Frabotta, chief of Navigation Branch, USACE Galveston District . “ The movement of commerce, through barge traffic, is an essential link between the Texas ports, Gulf regional ports and various facilities throughout the nation.”

Work is scheduled to begin in late April 2014 with an estimated completion in September 2014.

[mappress]

Press Release, April 13, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42
  2. 2Straatman: New female bow coupling for Jan de Nul
  3. 3Pilbara Ports: Eastern Harbor Revetment Project completes
  4. 4BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free