Manadhoo Harbor dredging in full swing

Infrastructure

The Maldives Transport and Contracting Company (MTCC) has just released the latest update on the Manadhoo Harbor development project.

MTCC

According to the company, the channel dredging operations and breakwater construction works have reached 50 percent progress so far.

MTCC also revealed that the ramp construction work began recently and that the installation of the jetty column is at 52 percent completion.

Scope of works for the project will include:

  • dredging and excavation operations of 29,038cbm;
  • construction of a 195m breakwater;
  • a 188m revetment;
  • a concrete bridge;
  • a ramp and installation of navigational aids.

The value of the project is MVR 30.3 million ($2 million).