Rohde Nielsen A/S recently completed beachfill operations on a project in Viveiro and Celeiro, Spain.

Rohde Nielsen

At the beginning of April 2020, the company started the works in the north-western part of Spain – for the Public Entity Portos de Galicia.

The project posed a great challenge for both the crew and the project team in the middle of the state of emergency that existed in Spain, due to the current Covid-19 pandemic.

Rohde Nielsen photo

In fact, the work consisted of dredging 50,000 m3 of which 10,000m3 were used to replenish the Covas beach. Also, the remaining mud and rock were dumped in open sea, at a distance of 15Nm.

The works were completed in the first week of July 2020.

“The project was perfectly executed by TSHD Magni R and Toste R, delivering an excellent result for our client and port users,” the company stated.