Milestone Reached on Boston Harbor Navigation Project

Business & Finance

The U.S. Army Corps of Engineers, New England District reached the milestone on April 5, 2019 of removing 4 million cubic yards of dredge material as part of Phase II of the three-phased Boston Harbor Navigation Improvement Project in Massachusetts.

Photo courtesy of the Corps

According to the Corps, approximately 7.7 million cubic yards of dredge material and weathered rock, and 200,000 to 500,000 cubic yards of hard rock remain to be removed before the project is fully completed by December 2021.

The Boston Harbor Federal Navigation Project is a $350 million partnership between the Army Corps, the Commonwealth of Massachusetts, and Massport.

The project involves deepening and improving various portions of the Boston Harbor Federal Navigation Project,” said Project Manager Jenifer Thalhauser, with the Corps of Engineers, New England District, Programs and Project Management Division in Concord, Massachusetts. “Project benefits will be realized with reduced tidal delays for cargo vessels and the capability of the Port of Boston to receive larger cargo ships which will benefit both regional and national commerce.”

This is a three phase project. Phase 1 (completed) involved constructing a Confined Aquatic Disposal (CAD) cell by dredging 1,000,000 cubic yards of material and disposing of that material at the Massachusetts Bay Disposal Site.

Once the CAD cell was constructed, maintenance dredging of approximately 800,000 cubic yards of silty material from portions of the 40-foot Main Ship Channel, the 40-foot deep Inner Confluence, and portions of the 35-foot deep channel, were placed into the newly constructed CAD cell.

The $12.8 million contract was awarded to Great Lakes Dredge and Dock of Oak Brook, Illinois, in September 2016. Construction started in July 2017 and was completed in December 2017.

Phase 2 (currently ongoing) involves dredging 11.7 million cubic yards of silt, blue clay, till and weathered rock. The $122.2 million contract was awarded to the Joint Venture of Cashman Dredging, Inc. and Dutra Group in February 2018.

Construction started in July 2018 and is anticipated to be completed in October 2021. The milestone of dredging 4 million cubic yards of material for phase 2 was reached on April 5, 2019.

Around 11.7 million cubic yards of material will be removed from the following components of the Boston Harbor Federal Navigation Project: deepening and widening the Broad Sound North Channel to -51 feet Mean Lower Low Water (MLLW); deepening and widening the Main Ship Channel to the Conley Terminal, including the turning basin to -47 feet MLLW; and deepening the President Roads Anchorage and deepening the lower Reserved Channel to -47 feet MLLW.

The dredge material is being placed in the Massachusetts Bay Disposal Site (MBDS), approximately 20 miles offshore of Boston Harbor, with the exception of a small fraction of the material that was placed as a cap to the Main Ship Channel Confined Aquatic Disposal (CAD) cell, just downstream of the inner confluence of the Chelsea and Mystic Rivers.

Phase 3 (future work) will involve removing approximately 200,000 to 500,000 cubic yards of hard rock. The contract solicitation is anticipated to be released in spring 2020 with the work getting underway later that year and when finished will then complete the entire Boston Harbor Improvement project.

Completion of the entire project is expected by December 2021.