Hilton Head Island Beach Renourishment Plan Revised

Business & Finance

As a result of weather related delays encountered since August 15, including the passage of Tropical Storm Hermine, the Town of Hilton Head Island has revised the schedule for the completion of the remaining segments of the Beach Renourishment Project.

Work on the southern half of the central oceanfront beach will continue to advance northward before stopping adjacent to southern Palmetto Dunes.

The active work site is currently beach area between 53 Dune Lane and 93 Dune Lane. This section is now expected to be complete in late September.

Work on the northern half of the central oceanfront beach, from southern Palmetto Dunes to Singleton Beach is now expected to take place during October.

The work here will start at the Singleton Beach and advance southward to the tie in.

[mappress mapid=”22995″]