Port of Ibiza Calls for Bids to Improve Quays

Business & Finance

Port of Ibiza Calls for Bids to Improve Quays

The Port Authority of the Balearic Islands (APB) has announced tender for redesign and improvement works of the South Ro-Ro Quay and the Fuel Quay at the Port of Ibiza.

The budget for the tender is €9,181,44.96, and the maximum execution period has been set to 15 months. The work will be carried out in two phases, so at least one of the two quays will remain operational at all times.

The project consists of replacing the current piling structure, which has deteriorated over time, with sheet-piling, thus making the quays stronger and more durable. The improvement work will be carried out on a surface area of 8,352 square metres, which includes two Ro-Ro ramps for loading and unloading, and the berthing lines on the South Ro-Ro Quay and the Fuel Quay, located on the Commercial Quays at the Port of Ibiza.

Deadline for bids is August 18th.

[mappress]

Press Release, July 11, 2014