Repairing the Great Sodus Bay East Breakwater

Breakwater Repair

Michigan-based Great Lakes Dock & Materials LLC has won a $6.7 million contract for critical repairs to the Great Sodus Bay East Breakwater.

Photo courtesy of USACE

The 100% federally funded project marks the largest investment ever in Great Sodus Bay by USACE, ensuring the harbor’s viability and contributions to the local and national economy and protection of some of the area’s best waterfront opportunities.

Work is targeted to begin in August with completion by fall 2025. The project will repair the full 1,653-foot length of the breakwater over two construction seasons.

Building on top of the original timber crib and concrete cap structure, construction will return the breakwater to its original height, seven feet above the lowest water level.

According to USACE, work is being conducted by marine barge along the breakwater. Marine traffic will not be obstructed, but vessels should exercise caution when navigating near the breakwater.