Maldives Transport and Contracting Company has just completed the K. Himmafushi Harbor Development Project – Phase 2.

MTCC
MTCC photo

Scope of works included:

  • harbor dredging operations of 19,895cbm,
  • channel dredging operations of 9,900cbm,
  • construction of a 251m quay wall,
  • a 15m breakwater,
  • a 311m revetment,
  • installation of concrete pavement (existing harbour – 1200sqm, new harbour – 1,443sqm),
  • construction of bridge (25m x 6m),
  • construction of jetty (63m x 4m),
  • installation of harbor streetlights, navigation lights and mooring blocks.

The value of the project is MVR 30.5 million ($1.9 million).